Introduction

One of the challenges with Hyperion Planning is the ability to move data between applications in real time.  A classic example of this is a P&L application with other modules that have greater detail.  The following is an example. Read more

 

Introduction

One of the huge benefits that available in Groovy Calculations is the ability to interact with a user, validate data, and act on the validation.  Now, we can interrupt form saves, stop Run Time Prompts from continuing, and communicate information back to the user. Read more

 

Introduction

We all know the Data Form validation rules are serviceable, but they are not robust.  When Smart View advanced and forms were opened in Excel, the validation logic developers had in JavaScript became useless.  Since then, we have really missed the ability to communicate with the user interactively with visual cues and validation rules that halted the saving of data.  Well, Groovy calculations to the rescue! Read more

 

What Is Groovy

Recently, Groovy scripting was added to ePBCS business rules as an option instead of the GUI, or the go-to scripting for you old-timers who still refuse to change.  These are defined in the Business Rule editor as Groovy calculations.  So, what is Groovy? Read more

 

Introduction

One of the problems with giving users of Hyperion Planning the ability to run calculations is opening up the possibility for all of them to run the same calculation at the same time.  Read more

 

I recently learned the importance of encrypted passwords in batch files. Without a password file, the scripts will still run, but the user is prompted to input a password in the command prompt after initialization. Encrypted passwords allow for the automation of these scripts. Shout out to Sumit Deo for his patience in guiding me through the initial process and helping me with my batch scripting skills along the way. Read more

 

I was recently testing out the performance of rulesets that were attached to forms, and ran into an issue that had me scratching my head. Certain rulesets were not running or even appearing on forms that they were attached to in the Planning application. Turns out, the rules had been corrupted in the transfer between Calc Manager and the Planning application Read more

 

Josh Forrest and I presented at last year’s Collaborate conference.  Along with that presentation, we wrote a white paper on the implementation of Hyperion Planning.  This paper included process of selecting a vendor, the project goals, requirements gathering, project methodology, and even the lessons learned once the implementation was completed.

The editors of OAUG asked us if they could publish the article in the summer edition, which was released this week.  The article was written closely with Abercrombie & Fitch and represents the process from the business, not from the consulting services, point of view.

The article can be downloaded here at www.oaug.org.  Access to the article requires free registration.

 

There are several ways to export data from Essbase on a large scale. Pulling it via Excel (Smart View or the Essbase Add-In) is not the best way to get large amounts of data when the goal is to move the data somewhere else, so this option will not be covered.

Database Export

The easiest method is to export all the data from a database by exporting the database.  This can be done in EAS.  This method is easy to automate with Maxl, but has little flexibility with formatting and the only option is to export all the data.  It can be exported in column format so the data can easily be loaded into another data repository.  If the data needs to be queried, or manipulated, this is a good option.   Read more

 

Everybody knows the quickest way from point A to point B is a straight line.  Everybody assumes that the path is traveled only one time – not back and forth, over and over again.  I see a lot of Essbase calculations and business rules, from experienced and novice developers, that go from point A to point B taking a straight line.  But, the calculation travels that line multiple times and is terribly inefficient.

Here is a simple example of a calculation.  Assume the Account dimension is dense, and the following members are all members in the Account dimension.  We will also assume there is a reason to store these values rather than making them dynamic calc member formulas.  Most of these are embedded in a FIX statement so the calculation only executes on the appropriate blocks.  To minimize confusion, this will not be added to the example.

Average Balance = (Beginning Balance  Ending Balance)  / 2;
Average Headcount = (Beginning Headcount   Ending Headcount) / 2;
Salaries = Average Headcount * Average Salaries;
Taxes = Gross Income * Tax Rate;

One of the staples of writing an effective calculation is to minimize the number of times a single block is opened, updated, and closed.  Think of a block as a spreadsheet, with accounts in the rows, and the periods in the columns.  If 100 spreadsheets had to be updated, the most efficient way to update them would be to open one, update the four accounts above, then save and close the spreadsheet (rather than opening/editing/closing each spreadsheet 4 different times for each account).

I will preface by stating the following can respond differently in different version.  The 11.1.x admin guide specifically states the following is not accurate.  Due to the inconsistencies I have experienced, I always play it safe and assume the following regardless of the version.

You might be surprised to know that the example above passes through every block four times.  First, it will pass through all the blocks and calculate Average Balance.  It will then go back and pass through the same blocks again, calculating Average Headcount.   This will occur two more times for Salaries and Taxes.  This is, theoretically, almost 4 times slower than passing through the blocks once.

The solution is very simple.  Simply place parenthesis around the calculations.

(
Average Balance = (Beginning Balance  Ending Balance)  / 2;
Average Headcount = (Beginning Headcount   Ending Headcount) / 2;
Salaries = Average Headcount * Average Salaries;
Taxes = Gross Income * Tax Rate;
)

This will force all four accounts to be calculated at the same time.  The block will be opened, all four accounts will be calculated and the block will be saved.

If you are new to this concept, you probably have done this without even knowing you were doing it.  When an IF statement is written, what follows the anchor?  An open parenthesis.  And, the ENDIF is followed by a close parenthesis.  There is your block!

"East"
(IF(@ISMBR("East"))
    "East" = "East" * 1.1;
ENDIF)

I have seen this very simple change drastically improve calculations.  Go back to a calculation that can use blocks and test it.  I bet you will be very pleased with the improvement.